March 9, 2017
Our LINK community has the south road located off Sutton Drive base material installed. We are expecting the curbs to be installed in the coming weeks. Read More...
February 8, 2017
Our LINK community has reached 2 major milestones in the month of January; we officially have power and gas on the entire site! Read More...
January 16, 2017
The Link site continues to grow as we move into 2017. The main gas line work is complete and Union Gas meters are installed, the gas line... Read More...
December 9, 2016
Milestone by milestone, the Link community is progressing quickly. The main road of Sutton Drive will be taking shape in the coming... Read More...
November 2, 2016
The Link buildings will hit some major milestones in the month of November. The main gas line to the buildings will be installed next week... Read More...