November Construction Update at Realm Condominiums | Burlington New Construction Progress

As November comes to a close, Realm by ADI Development Group continues to show steady progress across both towers. From interior suite finishing to exterior detailing and site work, our construction teams remain focused on delivering a high-quality, modern condominium community in the heart of Burlington.

This month’s construction update highlights the latest milestones in Building D and Building C, giving future homeowners clear insight into how their new home is taking shape. 

 
Building D Construction Progress — November Update 

Building D continues to advance across all major scopes of work. Several key interior and exterior milestones have been reached, helping prepare the building for upcoming finishing phases. 

Interior Progress 

  • Block walls are now fully completed, marking a significant structural milestone 
  • Hallways and exterior drywall are fully boarded, allowing finishing crews to continue working efficiently 
  • Suite finishes from the Ground Floor to the 13th Floor are actively progressing, with trades working floor-by-floor 

Mechanical & Amenity Work 

  • Mechanical Penthouse (MPH) activities and elevator installation are moving forward as scheduled 
  • Amenity areas are now in the finishing stages, offering a first look at the elevated lifestyle spaces future residents will enjoy 

Exterior Improvements 

  • Railing and cladding installation are ongoing 
  • Siding installation at the MPH continues to advance 

These updates move Building D closer to its final stages as we head toward winter and prepare for upcoming construction phases. 

 

 


Building C Construction Progress — November Update 

Building C has seen equally strong momentum this month. Teams continue to advance interior finishes, lobby design work, and exterior building elements. 

Interior Progress

  • Hallways and exterior drywall have been fully boarded, enabling interior finishing to continue seamlessly 
  • Suite finishes from the Ground Floor to the 13th Floor are underway, with consistent progress across all levels 

Mechanical & Lobby Work 

  • MPH activities and elevator installation are ongoing 
  • Lobby millwork has begun, offering a preview of the warm, modern arrival experience planned for Realm residents 

Exterior & Site Work 

  • Railing and cladding installation continue across the building 
  • Road base asphalt has been completed, shaping future community circulation 
  • Parking level traffic topping and painting are progressing well 

These milestones keep Building C on track as we transition into the next phase of construction. 
 

 
Realm Condos: Moving Closer to Completion 

The November construction progress at Realm reflects ADI Development Group’s ongoing commitment to quality, efficiency, and long-term value for our homeowners. With interior finishes advancing and exterior work taking shape, both towers continue to move closer to the final stages of development. 
Thank you to all future residents for your continued trust and enthusiasm. We look forward to sharing another update next month as Realm continues to rise in Burlington’s thriving real estate landscape. 
 
Explore remaining opportunities to own at Realm Condominiums today. 
 

Make a Friend a Neighbour – and Earn Up to $100,000 

Know someone who would love life at Realm? With our “Make a Friend a Neighbour” referral program, both you and your friend can benefit: 

  • You’ll earn $10,000 for each successful referral 
  • Your friend receives $5,000 toward their new home 
  • Up to 10 referrals allowed per homeowner!

It’s our way of saying thank you for helping us grow a vibrant, connected community. 
To learn more or book a private tour, contact: 


Kayla Curran 
📧 kayla.curran@adidevelopments.com 
📞 (647) 956-4576 

Stay tuned for next month’s construction update — and thank you for being part of the Realm story.